|
Projects & Operations
-
Project Development
NMC has commenced recruitment of an
operational management team who will supervise
the development aspects of the project and
then conduct operations. A three to four-year
mining project is planned for the Shinas-Hatta
deposits followed by development of the
Ghuzayn deposits south of Sohar.
Project implementation requires NMC to secure
a final Environment Permit for the whole
project, grant of Mining Leases and then
development permission from local
Municipalities and Government utilities.
NMC will undertake a memorandum of
understanding with OMCO to secure cooperation
and use of OMCO facilities and utilities
during process plant construction and
subsequent operations at Lasail.
We propose to setup a small analytical
laboratory onsite for process control, mine
grade control and exploration assaying.
NMC also intends to arrange an Offtake
agreement for the concentrate with OMCO,
however they have decided to blend the NMC
material with +30% Cu imported concentrate,
which means that some of NMC’s product will be
traded offshore through the new Sohar port.
Waste disposal of process tailings is a major
issue with the Government. Through cooperation
between NMC and government ministries a
suitable site has been selected. Detailed
design work is currently underway with
preliminary approval and construction to
commence soon. The tailings dam will be ready
for commissioning of the new mill.
We are confident that the technical merit of
our proposals will win over environmental
protagonists and allow grant of the final EIA
Permit for this project.
Process Plant Engineering
In July 2004 NMC purchased the Lasail
Concentrator and associated infrastructure
from the Government entity OMCO and signed a
lease Agreement over operational areas to
allow NMC consultants to evaluate the plant
condition and permit rehabilitation of the
facility as well as engineer an
environmentally acceptable tailings storage
scheme.
OMCO will supply power, gas and domestic
water, however the process water will be
sourced from the abandoned Aarja mine which is
also the preferred tailing storage site.
Following the Feasibility assessment by
Ascentis an associated engineering group
Vertex was selected in November 2004 to
conduct the
Engineering-Procurement-Construction-Management.
This company was later released and McNally
Bharat of India was brought in to complete the
engineering design and assist with procurement
and construction supervision.
There have been many delays to the project due
to operational and permitting issues. These
have been mostly overcome with the new
incoming management team. It is expected that
the mill will be commissioned in November
2006, producing copper before the end of the
year.
Metallurgy
Testwork on a number ore type blends from the
three main deposits was conducted to simulate
the characteristics of ores to be processed at
various stages in the development schedule.
Results were very encouraging because the
blended ores gave a similar and in some cases
better recovery of copper to concentrate than
the previous tests. This provides confidence
that blending or ores to provide a more
uniform plant input will result in good
operational performance. The testwork is an
ongoing process to determine the optimal
reagents to maximise recovery and production.
Analysis is continuing to determine ways of
overcoming bottlenecks in the process produced
by the treatment of higher grade ores. This
has resulted in having to reduce the overall
throughput of the mill. This analysis will
also investigate ways to further increase the
throughput beyond the original design levels.
Mine Design
To ensure good topographic control of the
Hatta minesites NMC conducted orthophoto
mapping using existing high-quality colour
aerial photography of the area to produce a
detailed contour plan in which to base its
engineering design of the mining
infrastructure. This was supported by accurate
GPS locations of proposed building sites and
existing drillholes for pit planning purposes.
Environmental approval has been obtained for
the wadi bund wall road and safety bund walls
around the pit perimeters as well as the waste
dumps west of the Hatta pit where it is
proposed to site a crusher to produce
aggregate and industrial stone from these
Hatta area mine site layout wall rocks.
Top
|